- Advantages and disadvantages.
- Gantt Chart
Activity No. | Descriptions of activities | Time required |
1 | Ground preparation | 1 weeks |
2 | Laying foundation | 2 weeks |
3 | Construction of pillars | 3 weeks |
4 | Construction of walls (can start after 1 week of the start of the activity 3 | 4 weeks |
5 | Roofing (can start only after the completion of the activity 3) | 2 weeks |
6 | Interiors (can start as soon as 50 % of the activity 4 is completed) | 3 weeks |
7 | Finishing and handover (can start only after the completion of the activity 6) | 1 weeks |
Questions:
- Using the above information, construct a Gantt chart, and also calculate the total number of weeks needed to complete the project. [6 marks]
- Define the term ‘working capital’. Explain how the construction of a Gantt chart help B2S to manage its working capital. [4 marks]
![](https://teacherrk.com/wp-content/uploads/2021/12/IMG-20211229-WA0008-300x53.jpg)